The handover inspection of a new apartment in Poland is called odbiór techniczny (the technical acceptance of the flat from the developer): you walk through the unit with the developer's representative, record every defect in a signed protocol, and only then move on to the notarial deed that transfers ownership. It is the buyer's main chance to have defects fixed at the developer's cost rather than your own. For scale, the median new-build flat in Praga-Południe sold for PLN 744,923 in notarial transactions registered between 2024-11-17 and 2025-12-19 (RCN data).

What odbiór techniczny is, and how it differs from the final deed

You first sign the umowa deweloperska (the developer agreement, signed before a notary), pay instalments according to a schedule, and once the building is finished two separate events follow: the technical handover and the umowa przenosząca własność (the final deed that transfers ownership to you).

Odbiór techniczny is a physical inspection, roughly what English-speaking buyers call a snagging inspection. Its output is the protokół odbioru (the handover protocol), which lists visible defects, deviations from the design and remarks on finishing. The notarial deed, by contrast, is the legal transfer of title. Signing the protocol does not make you the owner, but it is your strongest evidence that a defect existed at handover and that you reported it in time.

The Developer Act of 20 May 2021 (ustawa deweloperska) regulates this stage directly. The buyer has the right to carry out the inspection and have remarks written into the protocol, and the developer must respond to them and repair accepted defects within deadlines set by law. The buyer may also bring an independent expert. If your contract is not signed yet, check how it describes the handover procedure; our guide to the developer agreement in Poland and what to check walks through the relevant clauses.

What determines how many defects you will find

The number and seriousness of your remarks depend on a few factors worth considering before the inspection date.

  • Handover standard. Most new flats in Warsaw are delivered in stan deweloperski (the developer standard, a shell ready for finishing): plastered walls, screed floors, windows, entrance door and installations brought into the unit. You check geometry, plaster quality, windows and utilities. If the flat comes fully finished, the checklist gets much longer. What the developer standard includes and what it leaves to you is explained in our article on the developer standard in Poland and finishing costs.
  • Season. Winter exposes heating problems and condensation on windows; summer exposes ventilation and overheating issues.
  • Light and time of day. An evening inspection in a flat without working lights is a classic reason for missed defects. Book a daytime slot and bring a strong torch.
  • Language. The protocol is in Polish and the representative may not speak English. If your Polish is limited, bring someone who can make sure your remarks are written down exactly as you mean them.

What a missed problem can cost: floor area, price per m² and defects

Defects are not the only thing to verify. The second key question is the actual floor area. The price in a developer agreement is calculated from the area, while the final area is confirmed by measurement after completion. The contract usually defines an acceptable tolerance and how the price is settled: you pay more if the flat is larger, or receive a refund if it is smaller. Each square metre of difference is worth roughly the median price per m² in your district.

Median primary-market figures from RCN (Rejestr Cen Nieruchomości, the register of prices from notarial deeds), transactions registered from 2024-11-17 to 2025-12-19:

DistrictMedian price per m² from developers (PLN)Median flat price (PLN)Median area (m²)
Praga-Południe15,707744,92347.6
Włochy14,308678,71447.1
Ursynów14,085723,01646.6
Bemowo13,624660,70746.9
Ursus12,773596,94643.5
Białołęka12,482574,79343.7

According to NBP, the average transaction price on Warsaw's primary market in Q2 2026 was PLN 16,783 per m². Even a small area discrepancy means real money. You can check actual transaction prices for your area, for example on the page with RCN transaction prices in Ursynów.

New apartment handover checklist: what to inspect

Use this table as a working odbiór techniczny checklist for a flat delivered in the developer standard. Print it and go through it room by room without skipping any space.

ElementWhat to checkHow to check it
Area and layoutMatch with the floor plan in the contract, wall positions, door openings, ceiling heightLaser distance meter, contract floor plan
Walls and ceilingsFlatness, cracks, damp stains, plaster quality in cornersLong straightedge, torch held at an angle
Floors (screed)Flatness, cracks, hollow spotsStraightedge, light tapping
Windows and balcony doorsOpening in every mode, seals, scratches on glass, sillsVisual check, operate each sash by hand
Entrance doorLocks, full set of keys, tight fit, damageVisual check, test every key
ElectricsPower in every socket, distribution board, labelled breakersSocket tester
Water and drainagePipe outlets, no leaks, meters and their readingsVisual check, photos of meters
HeatingRadiators or underfloor heating, valves, no leaksVisual check, confirm it heats up
VentilationAirflow in kitchen and bathroom ventsSheet of paper held at the grille
Balcony or terraceWaterproofing, slope, railings, tilesVisual check, spirit level

If the developer delivers the flat finished, add tiles, grout lines, sanitary fittings, kitchen fronts and appliances. If you plan to finish the flat yourself after handover, it helps to compare apartment fit-out packages in advance, so you know which defects in the shell matter most for the work that follows.

Step by step: how to handle the handover inspection in Poland

  1. Reread your contract before the inspection date. Find the clauses on the finishing standard, floor area and price settlement, the handover procedure and liability for defects.
  2. Ask the developer for documents and prepare tools. Get the floor plan with dimensions and the description of the standard. Bring a laser distance meter, spirit level, straightedge, torch, socket tester, masking tape and a charged phone.
  3. Decide whether to bring an expert. The law allows you to bring an independent inspector (inspektor budowlany or rzeczoznawca). An experienced specialist spots what an unprepared buyer misses.
  4. If you cannot attend, appoint a representative. Investors living abroad often send someone with a written authorisation. Agree in advance who signs the protocol on your behalf.
  5. Inspect systematically. Go room by room, top to bottom: ceiling, walls, windows, floor, installations. Mark each defect with tape and photograph it both close up and in context.
  6. Write everything into the protocol. Be specific: room, wall, type of defect. A phrase like "minor defects" does not protect you. If the representative disagrees with a remark, insist that it is recorded anyway.
  7. Record meter readings. Water, electricity, heat, each with a photo. They determine from when the bills are yours.
  8. Get a copy of the protocol and the keys. Make sure both parties have signed it and every remark is listed.
  9. Follow up and re-inspect. The law sets deadlines for the developer to accept or reject remarks and repair accepted defects. Keep all correspondence in writing and check each item again after repairs, before you go to the notary.

The full purchase sequence, from choosing a flat to receiving the keys, is covered in our guide on how to buy off plan in Warsaw.

Defects in a new build in Poland: what to do when you find them

Polish practice divides defects into two groups: wady istotne (material defects that prevent normal use of the flat) and wady nieistotne (minor defects that can be fixed without preventing you from living there). Which group a defect falls into shapes your next move.

Minor defects such as scratched glass, uneven plaster or damaged doors go into the protocol, the developer repairs them, and you can usually proceed to the final deed.

Material defects include leaks, structural problems, missing or non-working ventilation or heating, and significant deviations from the design. In such cases the buyer may refuse to accept the flat until the developer fixes them. Act carefully here and rely on an expert's written opinion.

Defects that appear after the deed are not automatically your problem either. You are protected by rękojmia (the seller's statutory liability for defects), so the developer remains responsible for hidden defects after the keys are handed over. To use that protection you need evidence: the protocol, photos, emails and letters.

Your money is protected separately: under the same Act, payments go into a residential escrow account (mieszkaniowy rachunek powierniczy) backed by the Developer Guarantee Fund (DFG) if the developer or the bank fails.

Common buyer mistakes during the handover

Most losses at this stage come from haste and trust in verbal promises:

  • Rushing the inspection. The representative may have several handovers that day. You do not have to match their pace; it is your flat.
  • Verbal promises instead of written remarks. "We will fix it, no need to write it down" is worth nothing. Anything missing from the protocol will have to be proven separately later.
  • Ignoring the floor area. Buyers often skip measurements and never compare them with the contract, although area directly affects the final price.
  • Signing the deed before material defects are fixed. After the deed your position weakens: you have to prove the defect and wait for repairs while already living there.
  • No photos and no copy of the protocol. Without them, any dispute becomes your word against the developer's.

How NAWROCKI Real Estate helps with the handover

NAWROCKI Real Estate is a buyer's agent for new-build flats in Warsaw. We work on your side throughout the purchase, not only on handover day:

  • we compare offers from many developers at once and check the developer's price per m² against real notarial transactions (RCN) in the district;
  • we read the umowa deweloperska and the information prospectus, with attention to clauses on floor area, finishing standard and the handover procedure;
  • we negotiate price and terms with developers;
  • we keep track of the payment schedule;
  • we help with the technical acceptance of the flat (odbiór techniczny), so the protocol is complete and every remark is specific.

In most developments we work with, the developer pays our fee, so for the buyer the service is usually free. If that is not the case, we tell you before we start.

If your handover date is approaching, or you are still choosing a new-build flat, contact NAWROCKI Real Estate and we will go through your contract and prepare for the odbiór techniczny together.

Frequently asked questions

What if the developer's representative refuses to record a defect?

Insist that every remark is written into the protocol, even if the representative disagrees with it. The protocol is your main evidence that the defect existed at handover. If they still refuse, photograph the defect, describe it in writing and send it to the developer by email or letter.

Can I refuse to accept the apartment because of defects?

If the defects are material, meaning they prevent normal use of the flat, the buyer may refuse acceptance until they are repaired. Minor defects are usually not grounds for refusal, but they must still be recorded in the protocol. Base the decision on an expert's opinion.

Can someone else do the handover if I live abroad?

Yes, many foreign investors send a representative with a written authorisation. Agree in advance who will sign the protocol on your behalf and make sure that person can read the Polish document and has your checklist.

What if a defect appears after I move in?

The developer remains liable for hidden defects after handover under rękojmia, the seller's statutory liability for defects. Document the defect with photos straight away and notify the developer in writing. Without evidence it is much harder to enforce your rights.

Districts in this article — check the data

This article in other languages: Polski · Русский · Українська · Deutsch · Türkçe

Read also

Flats matched to your budget

We'll match new-build flats to your budget

Pick a budget and a district to see current offers from developers right away. Add your e-mail and we'll send the link too.

Budget

When do you plan to buy?

By submitting, you consent to the processing of your data to prepare and send the selection. Privacy policy

← All articles